Loading…
Venue: Campania A/B clear filter
Wednesday, September 16
 

1:30pm MDT

Stormwater Reuse and Wetland Retention - Industrial Development Case Study
Wednesday September 16, 2026 1:30pm - 2:00pm MDT
A railyard and logistics centre Staged Master Drainage Plan (SMDP) outlines the stormwater management strategy for a 536‑hectare industrial development in southern Alberta. Prepared to meet strict local authority guidelines in a closed basin, the plan aims to manage post‑development runoff, protect retained Crown‑claimed wetlands, and integrate local and regional drainage infrastructure. The SMDP emphasizes adaptive management and long‑term monitoring to address uncertainties in groundwater–wetland interactions and ensure ongoing regulatory and environmental compliance.
The site consists primarily of cultivated land with flat topography and numerous wetlands. Geotechnical and groundwater investigations identified variable till layers and shallow bedrock, with groundwater generally flowing toward wetlands and exhibiting seasonal fluctuations. These conditions informed the drainage design and wetland protection approach.
Stormwater management is centered on nine wet stormwater management facilities (SWMFs) designed to provide sediment control and water quality treatment, exceeding the local authority requirement for 85% total suspended solids removal. Several facilities are positioned to support wetland hydrology and include provisions for direct pumping where required. A regional stormwater trunk system conveys controlled outflows to an open channel and is sized to accommodate both onsite and upstream catchments.
Development is planned in six phases, with each phase extending the trunk system and constructing associated infrastructure. Due to the absence of feasible overland emergency spill routes, the trunk system is designed with increased capacity to manage extreme storm events.
Hydrologic modeling using PCSWMM shows reduced infiltration and groundwater recharge and increased surface runoff following development. To mitigate impacts on wetland hydroperiods, adaptive management measures are recommended, including seasonal or year‑round pumping and potential supplemental groundwater baseflow.
Speakers
NC

Neal Cody

Water Resources Engineer, Stantec

Wednesday September 16, 2026 1:30pm - 2:00pm MDT
Campania A/B 2nf Floor, Delta Hotel
  Stormwater
  • global Y

2:00pm MDT

Concept to Construction: Lauderdale Dry Pond
Wednesday September 16, 2026 2:00pm - 2:30pm MDT
The Lauderdale neighbourhood in Edmonton ranked as one of the higher priority flood risk neighbourhoods in EPCOR’s SIRP basin ranking system. The neighbourhood is partially separated with some dedicated storm sewers, but also portions of combined sewers with lower level of service that tend to exhibit drainage issues during intense rainfall. Stantec Consulting was retained by EPCOR to implement a flood mitigation dry pond and storm sewer upgrades in the neighbourhood to reduce the flood risk and improve the level of service for the drainage system. Starting as a concept design evaluation, the project continued through to a design phase and now implementation with construction starting in late 2025. Some unique challenges arose during the project including the assessment of a complex drainage network using a 2D hydraulic model, special design considerations for implementing a stormwater management facility in Edmonton’s largest fully fenced off-leash dog park, and a portion of dual-micro tunneling for deep sanitary and storm sewer installation. This presentation will showcase the unique challenges, creative solutions and lessons learned of this complex drainage upgrade in a sensitive area.
Speakers
DB

David Burton

Water Resources Engineer, Stantec Consulting
David is a water resources engineer at Stantec's head office in Edmonton. He has 14 years of experience in urban drainage planning and design for urban flood mitigation infrastructure. Currently he acts as the Urban Water Resources Engineering Disciple Lead for Western Canada.
Wednesday September 16, 2026 2:00pm - 2:30pm MDT
Campania A/B 2nf Floor, Delta Hotel

2:30pm MDT

Gasification Projects, Pitfalls, bear traps, dust devils and opportunities
Wednesday September 16, 2026 2:30pm - 3:00pm MDT
Insights from a quarter of century of gasification projects experience. This will be primarily focussed on biosolids and other sludges but will refer to other waste types.
 
Biosolids challenges will be reviewed briefly and then a step by step look at the critical stages of process and building a project including:
  • Feedstock characteristics, project planning and plant integration.
  • Importance of dewatering, drying and achieving thermal balance.
  • Gasification and pyrolysis design types.
  • Addressing emissions and contaminants, e.g. PFAS.
  • Understanding project financial feasibility: Products, markets and revenue.
  • A brief look at IQ Energy Technology Development and an update on our 12 dry tonnes per day gasification plant that is operational in Canada.
 
The object of the session is to look broadly at possible projects and what to be looking for and questions to ask, where the pitfalls and opportunities are from our developers 25+ years of project experience.
 
Speakers
CF

Charles Foster

IQ Energy Inc.

Wednesday September 16, 2026 2:30pm - 3:00pm MDT
Campania A/B 2nf Floor, Delta Hotel

3:30pm MDT

Integrating Stormwater Reuse for Irrigation and Wetland Replenishment in a closed basin – A residential development Case Study
Wednesday September 16, 2026 3:30pm - 4:00pm MDT
Urban stormwater management is increasingly required to balance flood mitigation, water quality improvement, and sustainable water use. The Cornerstone Phase 1 Storm Pond P project in northeast Calgary demonstrates how stormwater reuse can be integrated into conventional wet pond design to support both landscape irrigation and wetland replenishment while meeting stringent regulatory discharge and water quality objectives.
Storm Pond P services a 153.9 ha mixed residential and commercial catchment and was designed as a permanent wet pond with offline sediment chambers to achieve sediment removal targets exceeding 85% for particles ≥50 µm prior to discharge to Nose Creek. In addition to quantity and quality control, the system incorporates active reuse of stored stormwater to offset potable water demand and support downstream aquatic features. 
Stormwater reuse for irrigation is achieved through controlled pumping from the pond’s permanent storage zone between defined lower and upper normal water levels. Reclaimed water is used to irrigate approximately 15.3 ha of parks, sports fields, school sites, and landscaped open spaces, with irrigation demand and withdrawal rates governed by evapotranspiration, soil infiltration capacity, and seasonal operating rules. The reuse system is explicitly modeled within a continuous PCSWMM framework to evaluate long-term water balance performance and ensure compliance with watershed runoff volume targets.
In parallel, stormwater is reused to replenish an adjacent constructed wetland (Wetland Q), providing ecological support and additional volume management benefits. Automated control rules regulate pumping based on pond water levels and seasonal conditions, ensuring wetland replenishment without compromising flood storage capacity.
This case study illustrates how storm ponds can function as multi-purpose water infrastructure, integrating stormwater reuse, irrigation efficiency, and wetland sustainability into urban drainage systems. The approach offers a transferable framework for municipalities seeking resilient, climate-adaptive stormwater solutions that extend beyond traditional conveyance and detention objectives.
Speakers
NA

Nadir Abdalla

Stantec Consulting Ltd

Wednesday September 16, 2026 3:30pm - 4:00pm MDT
Campania A/B 2nf Floor, Delta Hotel

4:00pm MDT

Safety Improvements at Existing Stormwater Management Facility Wet Ponds
Wednesday September 16, 2026 4:00pm - 4:30pm MDT
EPCOR Water Services owns and operates over 240 stormwater management facilities in the City of Edmonton and has been undertaking various initiatives to improve the safety of these facilities - in particular wet ponds. In 2017, EPCOR completed an initial safety review which included a jurisdictional review of existing SWMF safety practices, an assessment of gaps between EPCOR's SWMF safety standards and those of other jurisdictions, and identification of improvements to EPCOR SWMF standards. In 2019, Stantec conducted field inspections of all of EPCOR's wet ponds and completed risk assessments and identification of safety deficiencies to prioritize which sites required immediate attention. Since this field program, EPCOR has continued to refine their risk assessments of these facilities and has commenced design and construction efforts with Stantec on 10 wet ponds throughout Edmonton.  
A challenging aspect of wet pond safety is balancing the need for access to the pond for maintenance/inspections, visibility around the shoreline, and barriers for public access (which often inhibit maintenance access & visibility). EPCOR and Stantec have been developing a vegetative barrier approach using plant species that complement the existing vegetation, provide deterrents to for public access, and include view-corridors for maintenance and operations purposes. Surveys were used to collect resident feedback on a variety of topics including existing use of the space around the wet ponds, proposed plant species, and reiterating the importance of safety around these stormwater facilities. 
This presentation will share the story of assessment, risk identification, public consultation, and design & construction efforts which were undertaken (and continue to be pursued) to improve safety at EPCOR's wet ponds. 
Speakers
avatar for Sara Kardash

Sara Kardash

Water Resource Engineer, Stantec Consulting Ltd.
Sara is a Water Resource Engineer from Edmonton, AB, who works on stormwater improvement projects including dry ponds, wet pond safety, outfall rehabilitation, and low impact development.
Wednesday September 16, 2026 4:00pm - 4:30pm MDT
Campania A/B 2nf Floor, Delta Hotel
 
Thursday, September 17
 

9:00am MDT

From Innovation to Application: Dynamic Single-Stage RO for High-Recovery PFAS Removal in Drinking Water Treatment
Thursday September 17, 2026 9:00am - 9:30am MDT
Dynamic Single-Stage Reverse Osmosis (DSSRO) technology offers a transformative approach to the removal of per- and polyfluoroalkyl substances (PFAS) in drinking water treatment. PFAS are persistent synthetic chemicals that present significant public health risks due to their resistance to conventional treatment methods and their tendency to accumulate in the environment. As regulatory standards for PFAS in drinking water become increasingly stringent, utilities require advanced, reliable, and sustainable solutions.
Traditional reverse osmosis (RO) systems, while effective at removing a broad spectrum of contaminants, are often constrained by membrane fouling, high energy consumption, and the generation of large volumes of concentrated waste streams. DSSRO addresses these limitations through an innovative single-stage, semi-batch membrane array and a unique two-pump configuration. This design enables high recovery rates, often exceeding 85%, while minimizing the volume of PFAS-laden concentrate. By maintaining high crossflow and regulating flux, DSSRO reduces fouling and scaling, which in turn decreases the frequency and intensity of chemical cleaning required. This not only lowers operational costs but also extends membrane life and reduces environmental impact.
Pilot studies at multiple drinking water facilities have demonstrated DSSRO’s technical feasibility and sustainability, consistently achieving permeate PFAS levels below detection limits. The system’s high recovery rates significantly reduce concentrate output and source water demands, making it particularly attractive for utilities operating under water scarcity or strict discharge regulations. By minimizing the volume of PFAS-laden concentrate that requires disposal, DSSRO helps utilities address one of the most challenging and costly aspects of PFAS treatment, safe and responsible concentrate management. DSSRO’s adaptability allows it to be integrated into existing treatment trains, complementing other processes such as enhanced coagulation, oxidation, and ultrafiltration.
Operational data from these pilots highlight the system’s robust performance under varying water qualities and operational conditions. Automated controls, real-time monitoring, and remote data logging further enhance reliability and facilitate rapid response to changing influent characteristics. These features support utilities in meeting evolving regulatory requirements and public health goals.
This presentation will explore the technical and operational advantages of DSSRO, share pilot results, and discuss practical considerations for implementation. By advancing the application of DSSRO technology, this work aims to inspire new standards for PFAS removal and support the delivery of safe, sustainable drinking water for communities.
Speakers
DM

Daniella Mosqueda

Process Engineer, Veolia
Daniella Mosqueda has over 20 years of water treatment and engineering experience including process design, optimization, and research and development in the fields of ultrafiltration, reverse osmosis, and membrane bioreactors for drinking water, wastewater and water reuse applications... Read More →
Thursday September 17, 2026 9:00am - 9:30am MDT
Campania A/B 2nf Floor, Delta Hotel

9:30am MDT

Keeping Control Systems Running - Practical Maintenance for Water & Wastewater
Thursday September 17, 2026 9:30am - 10:00am MDT
This presentation explores best practices for maintaining Industrial Control Systems (ICS) in the water and wastewater sector. We will examine lifecycle considerations for PLCs, SCADA platforms, wireless communication options, and supporting components, providing practical recommendations for sustaining these critical assets. Key topics include strategies for backups, firmware management, system health checks, and determining appropriate spare hardware levels to ensure reliability. Emphasis will be placed on cybersecurity and how proactive maintenance strengthens facility security. To ground these concepts, we will review a real-world ICS maintenance plan for a the new Town of Esterhazy Regional Water Treatment Plant, highlighting architecture and upgrade planning. Modern trends such as remote access, cloud integration, and AI driven tools will also be discussed, equipping attendees with actionable insights to improve resilience and performance in their own operations.
Speakers
avatar for Gregory Smythe

Gregory Smythe

Technical Sales Engineer, Delco Automation
Greg Smythe graduated from the University of Saskatchewan in 2009 with a Bachelor of Science in Engineering Physics. Shortly after graduation, Greg began work with Delco Automation as an automation developer where he specialized in programming and commissioning PLCs, HMIs, SCADAs... Read More →
Thursday September 17, 2026 9:30am - 10:00am MDT
Campania A/B 2nf Floor, Delta Hotel

10:00am MDT

Managing more than Water - Technical Challenges of Designing the City of Prince Albert’s Raw Water Pumphouse
Thursday September 17, 2026 10:00am - 10:30am MDT
Prince Albert’s Raw Water Pump House is situated on the south bank of the North Saskatchewan River and draws river water through an existing open‑orifice intake structure to supply the City’s water treatment, storage, and distribution systems. Designed in 2019 and substantially completed in 2022, the facility required the design of multiple process systems beyond conventional raw water pumping to support reliable year‑round operation. 


Because the intake lacks end‑of‑pipe screening, multiple resident fish species are drawn into the facility. To comply with the Department of Fisheries and Oceans fish‑protection requirements, the design team evaluated and integrated systems capable of low‑shear handling, separation, and safe return of live fish to the river. These evaluations included assessment of hydraulic conveyance velocities, physical barriers, behavioral barriers, bypass routing, fish‑handling equipment, and operational controls to avoid impingement and entrainment hazards.


The River also transports significant quantities of organic debris (branches, leaves, vegetation) along with suspended solids including sand, silt, and fine sediments. The facility therefore required both primary sedimentation capacity and an automated solids‑handling process that minimized operator intervention while providing an environmentally compliant means of solids removal and disposal. 


A major seasonal risk factor is frazil ice formation. During early winter, supercooled flow conditions in the North Saskatchewan River leads to the generation of frazil ice crystals, which can accumulate within the intake pipeline and form bridging blockages that restrict or entirely obstruct raw water flow. The design incorporated a frazil‑ice mitigation and management system capable of maintaining hydraulic capacity during high‑risk periods.


In 2023, the Raw Water Pump House was recognized by the Association of Consulting Engineering Companies – Saskatchewan for its innovative integration of fish‑protection systems and its robust design approach to managing frazil ice, high sediment loads, organic debris, and river flooding events.
Speakers
avatar for Lance Fradette

Lance Fradette

Project Engineer, AECOM Canada Ltd.
Lance is a project engineer with AECOM's Water business line out of the Saskatoon office. In his 14 years with AECOM he has worked primarily in process engineering of water & wastewater pump stations as well as the design of water transmission and sewage force mains. His engineering... Read More →
Thursday September 17, 2026 10:00am - 10:30am MDT
Campania A/B 2nf Floor, Delta Hotel

11:00am MDT

Membrane Technology in Action - UFRO vs. Hollow Fiber Nanofiltration Through Real World Application
Thursday September 17, 2026 11:00am - 11:30am MDT
Description:
 
This presentation compares ultrafiltration/reverse osmosis (UF/RO) and hollow fiber nanofiltration (HFN) systems through a detailed case study using real-world performance data. Key factors such as recovery, water stability, chemical use, footprint, and capital and O&M costs are evaluated against modeled projections. Results highlight each technology’s strengths and limitations in meeting Canadian Drinking Water Guidelines while identifying potential savings in energy, chemical demand, and overall system costs. Attendees will gain practical insights into technology selection, process optimization, and design considerations for future water treatment applications.


Abstract:


Membrane treatment systems play a critical role in ensuring reliable, high-quality drinking water for communities. Selecting the appropriate technology requires careful evaluation of system performance, capital and O&M costs, and operational considerations. With both ultrafiltration/reverse osmosis (UF/RO) and hollow fiber nanofiltration (HFN) technologies available, understanding how each performs under comparable conditions is essential to optimizing plant design and operational performance. 


A detailed case study is provided comparing a full-scale UF/RO system with a hollow fiber nanofiltration installation treating similar water sources. The comparison evaluates key parameters including recovery rates, treated water stability, chemical consumption, operations and maintenance (O&M) costs, capital costs, and system footprint. 
Real performance data is analyzed and compared to modeled projections to evaluate how theoretical expectations align with field results. Findings illustrate the strengths and limitations of each approach in achieving treated water that meets Canadian Drinking Water Guidelines. The results demonstrate a potential of savings in energy and water efficiencies, chemical demand, plant footprint and capital and O&M costs between the two systems. 
This analysis provides operators and engineers with practical insights into technology selection, process optimization, and total cost-of-ownership considerations for future water treatment projects. Insights are provided through comparison of real-world applications of UF/RO and hollow fiber nanofiltration systems, identifying capital and operational considerations and applying field data and modeling to improve future systems design and technology selection. 
Speakers
KH

Kelsie Hubick

Technical Sales Engineer, Delco Water
Kelsie is a professional engineer with 6 years of experience in both the industrial and municipal drinking water sectors focusing on membrane and media filtration systems, cooling towers, boilers and wastewater treatment. Five of those years being with Delco Water, she has been involved... Read More →
Thursday September 17, 2026 11:00am - 11:30am MDT
Campania A/B 2nf Floor, Delta Hotel

11:30am MDT

Moosomin Water Treatment Plant Upgrades
Thursday September 17, 2026 11:30am - 12:00pm MDT
The historical water treatment plant (WTP) at the Town of Moosomin produced finished water that was generally in compliance with Maximum Acceptable Concentration (MAC) parameters such as arsenic, iron, and manganese. However, the plant had no process to improve the aesthetics of the finished water which were elevated TDS and hardness. The existing graver style filters had also far exceeded their design life and required increasing operator attention to maintain compliant effluent qualities.
To achieve improvement to water aesthetics, KGS Group proposed the implementation of biological filtration followed by membrane filtration technology. The biological filtration system termed Mangazur offered by Veolia was piloted with very favorable results reducing manganese from 1.2 mg/L to less than 0.05 mg/L and filtration rates as high as 19.5 m/hr (8 gpm/ft2). Given the mature state of membrane technology, the membranes were not piloted.
Based on the success of the pilot, the decision was made to utilize Mangazur for full-scale implementation. Two 2.14 m diameter filter vessels were selected each with filtration areas of 3.57 m2 for a total of 7.14 m2. At a rate of 19.5 m/hr, the two filters could each produce treatment rates up to 70 m3/hr for a total pre-treatment rate of 140 m3/hr.
The membrane filtration system that followed the Mangazur consisted of two primary Reverse Osmosis (RO) skids that operated at 75% recovery and a third brine skid that treated the reject water from the two primary units operating at 50% recovery. The purpose of the brine skid was to increase overall recovery which was estimated at 88% for the complete membrane system. This 13% reduction in rejected wastewater took significant pressure off the existing sanitary infrastructure.
The primary skids were each sized to produce 39 m3/hr for a total of 78 m3/hr. The brine skid was sized to produce 13 m3/hr and the overall total membrane production was 90 m3/hr; total feed rate with both primary skids running was 103 m3/hr.
To produce a stable finished water, the design blended 25% of the Mangazur effluent with the membrane permeate. With both membrane skids running the blend rate was 22 m3/hr.
Although the raw water supply wells had been MPA tested confirming groundwater, the proximity to the lake presented the possibility that the supply wells could be declared GUDI in the future. Given this possibility additional measures were taken during the design to help accommodate a potential well designation change. This included the installation of UV disinfection and a cartridge filter rated for 3-log Crypto/Giardia on the blend line. Virus inactivation will still be provided through chlorination with CT provided by the treated water reservoir.
The historical WTP utilized chlorine gas for primary and secondary disinfection. Given the proposed treatment changes significantly reduce the total chlorine demand, the upgraded design moved to use sodium hypochlorite. The chlorine gas feed and associated equipment were abandoned.
The full scale WTP was commissioned in late 2025 and is currently producing high quality finished water for the community.
Speakers
DG

David Germin

Municipal Engineer, KGS Group
Mr. Germin completed a B.A.Sc. in Environmental Systems Engineering at the University of Regina in 2012. His fourth-year final project focused on the economic feasibility of regional water treatment plants within Saskatchewan. Since joining KGS Group, Mr. Germin has provided significant... Read More →
Thursday September 17, 2026 11:30am - 12:00pm MDT
Campania A/B 2nf Floor, Delta Hotel

1:30pm MDT

Deciding to Deliver: How We Defined the Saskatoon Waterworks Program
Thursday September 17, 2026 1:30pm - 2:00pm MDT
The Saskatoon Waterworks Program is a group of Saskatoon Water capital projects including several upgrades at the existing Avenue H Water Treatment Plant (WTP) and the addition of a second Water Treatment Plant.  The challenge for the Waterworks Program is taking the conceptual level master planning work, existing capital plans, and the decision to build a second WTP, to develop an actionable 500 million dollar capital program that is expected to span over a decade. Starting in 2023 the team worked through their Program Definition phase; a more detailed set of plans to determine and document the program’s governance, scope, funding, sequencing, delivery model, and overall philosophy.    
One of the pillars of the Program was the use of decision science methods to make decisions in a systematic way.  Several different methods were used in order for the tool to fit the decision and not the other way around.  Decision Quality (DQ) is a framework which ties together not just decision tools but also an overall philosophy of what makes a good decision and how to integrate uncertainty and risk into making long term decisions.  DQ was developed out of Ron Howard’s research at Stanford University and has been the benchmark for making good decisions since the 1960s.   Companies such as Eli Lilly and Exxon Mobil have integrated DQ into their standard business practices.   Saskatoon Water has utilized DQ for several years including for the decision to build a second WTP.  Tools such as Choosing by Advantages, monetary equivalents, multi-criteria analysis, and decision tree analysis were used to examine project delivery methodology, process improvements, technology selection, site planning, and forecasting scenarios.  Each of these decisions were unique and required the correct tool for the situation.  
An important early component of the Program Definition phase was the identification of key decisions that needed to be made and the order in which they needed to be made.  After finalizing major decisions, the Program Definition Phase progressed to producing Design Intent Documents; a combination of design philosophy, conceptual level design, and project requirement documents for the future projects.  These documents gave a technical foundation for moving to the execution phase of the Program.  Collaborative delivery was identified as being important to Saskatoon Water to get the best project outcomes possible from the Waterworks Program.   Construction Management at Risk (CMAR) was chosen as the delivery model because it was found to fit best with the expectations of the City of Saskatoon.  The Program has progressed to the design phase for the first set of projects with construction anticipated to begin in 2027.
The presentation will explore the journey of the Waterworks Program from choosing a direction to creating a coherent vision of what the Program hopes to accomplish over a ten year period.  There will be a focus specifically on lessons learned related to applying decision science, governance items, and organizational change management as it relates to selecting and implementing a new project delivery framework.
Speakers
RS

Rob St. Pierre

Sr. Process Engineer, City of Saskatoon
Rob St. Pierre is the Sr. Process Engineer for the City of Saskatoon’s Water Treatment Plant and member of the Waterworks Program Team. He has 17 years experience in Water Treatment and has held a variety of roles including engineering roles, commissioning of capital projects, project... Read More →
Thursday September 17, 2026 1:30pm - 2:00pm MDT
Campania A/B 2nf Floor, Delta Hotel

2:00pm MDT

Delivering Resilient Water and Wastewater Infrastructure for the Stoney Nakoda First Nation in Cold Climate Mountain Regions: Engineering Through Winter Construction Constraints
Thursday September 17, 2026 2:00pm - 2:30pm MDT
The Stoney Nakoda Nations is undergoing population and development growth associated with expanded resort operations, increased staff-accommodation demand, and new residential areas. This growth has created additional loading on the existing water and wastewater treatment systems, necessitating upgrades to increase treatment capacity and improve system resilience. This abstract summarizes the engineering assessment, design approach, Indigenous partnership, and construction methods used to advance the Water Treatment Plant (WTP) and Wastewater Treatment Plant (WWTP), with particular emphasis on cold-weather construction challenges, mitigation strategies, and adaptive planning required to meet revised design horizons under extreme winter conditions.
A detailed evaluation by MPE, a division of Englobe, confirmed that both facilities were operating at or near their original design capacities. This finding initiated a multidisciplinary upgrade program. Initial tender pricing exceeded the pre-tender estimate by approximately 70%; however, a structured value-engineering process, combined with design optimization and early contractor involvement by Everest Construction Ltd., enabled the project team to align scope and budget without reducing required performance criteria.
Construction commenced in late fall 2025 and was executed under challenging winter conditions that required specialized mitigation measures. Glycol heating lines and insulated tarps were installed and continuously maintained to thaw frozen ground and enable earthworks and concrete placement. Despite these controls, moisture intrusion beneath tarps and thaw systems occurred, resulting in excessive moisture content within fill materials and subsequent failure to meet compaction requirements in affected areas. Unsuitable material was therefore removed and replaced to achieve design specifications. Additional challenges included temporary delays caused by a thaw unit tripping offline and intermittent suspension of construction activities during periods of extreme weather. High wind events posed safety risks and resulted in a tree falling within the active construction zone, requiring immediate site control measures. Collectively, these conditions highlighted the importance of robust cold-weather construction planning, real-time field adaptability, and proactive risk management to maintain quality, safety, and project continuity. The project demonstrates how treatment-facility upgrades can be implemented under winter constraints while maintaining quality control and operational continuity.
Operational continuity was a key driver throughout design and construction, as both facilities were required to remain online during the majority of the upgrade works. Temporary bypass systems, phased commissioning, and enhanced monitoring were incorporated to minimize service disruptions and protect treated water and effluent quality during construction activities. These measures reduced risk to the community while allowing upgrades to be implemented efficiently.
Beyond its technical achievements, the project provides meaningful socioeconomic benefits to the Stoney Nakoda Nations. Construction activities prioritized employment of local Nation members and engagement of Indigenous businesses, contributing to skills development, economic participation, and community self-reliance. The upgraded infrastructure directly supports future residential and economic development while safeguarding public health and environmental stewardship in a challenging mountainous setting. Collectively, the project illustrates how value engineering, winter-condition construction, and Indigenous partnership can converge to deliver resilient and sustainable water infrastructure.
 
Speakers
DD

Dr. Debjani Mukherjee

Project Engineer, MPE a Division of Englobe
Dr. Debjani Mukherjee, P.Eng., is a Process Engineer at MPE, a division of Englobe, who specializes in the design, construction, and commissioning of critical water infrastructure. With a PhD from the University of Windsor, her expertise spans the end-to-end lifecycle of critical... Read More →
Thursday September 17, 2026 2:00pm - 2:30pm MDT
Campania A/B 2nf Floor, Delta Hotel

2:30pm MDT

Owner's Perspective of Progressive Design Build of the Buffalo Pound Water Treatment Plant Renewal Project
Thursday September 17, 2026 2:30pm - 3:00pm MDT
This paper will present the vision of the Buffalo Pound Water Treatment Corporation in providing sustainable, high quality potable water, and the steps taken for the renewal of the Buffalo Pound Water Treatment Plant. Owners seeking cost certainty, schedule acceleration, and risk mitigation are looking at alternative delivery methods for critical infrastructure.  The Buffalo Pound Water Treatment Corporation explored various alternative delivery methods and found that for the Buffalo Pound Water Treatment Plant Renewal Project, progressive design build was the method of choice in delivering their vision.  The Renewal Project was one of the first to utilize progressive design build in the water sector. The Corporation will share their experiences and lessons learned so that others water utilities may benefit should they elect to proceed with alternative delivery methods. 


The paper will walk through:


1. the various procurement models that were evaluated and the one that was selected (progressive design build), 
2. the complexity of brownfield construction within an active water treatment plant,
3. the collaborative approach during the engineering phase, and,
4. the challenges encountered by the Corporation during the construction phase.


Speakers
BW

Barry Williamson

Senior Project Manager, Jacobs
Buffalo Pound Water Treatment Plant Renewal Project - Progressive Design Build
Thursday September 17, 2026 2:30pm - 3:00pm MDT
Campania A/B 2nf Floor, Delta Hotel

3:30pm MDT

Drinking Water Management in Saskatchewan
Thursday September 17, 2026 3:30pm - 4:00pm MDT
Safe drinking water is essential for the protection of public health and disease prevention and therefore is necessary for the health and well-being of Saskatchewan’s citizens. Drinking water management in Saskatchewan is legislated under The Environmental Management and Protection Act, 2010, The Waterworks and Sewage Works Regulations, The Public Health Act, 1994 and The Health Hazard Regulations. Water Security Agency (WSA) in Saskatchewan has the legislative authority to regulate water and wastewater treatment systems and enforce standards with respect to drinking water and wastewater quality in the province. WSA regulates municipal waterworks, private waterworks with greater than 18 m3 per day design flow, water pipelines connected to municipal waterworks, and water pipelines with 15 or more service connections. In addition, water sampling requirements for limited-scope water pipelines, as defined in The Health Hazard Regulations, are regulated by WSA. Saskatchewan Health Authority (SHA) regulates non-municipal public water systems and private semi-public water systems. Private non-public water systems used for domestic purposes (e.g., private household systems) are not regulated. This paper outlines the regulatory framework, water management activities including developing drinking water quality standards, source water protection measures, treatment, public perception and trust, monitoring and compliance undertaken by the WSA to implement the Safe Drinking Water Strategy in the province
Speakers
AT

Arasu Thirunavukkarasu

Manager, Water Security Agency, Government of Saskatchewan
Presenting paper
Thursday September 17, 2026 3:30pm - 4:00pm MDT
Campania A/B 2nf Floor, Delta Hotel

4:00pm MDT

Modular Water Treatment: A Collaborative Approach for Sunchild First Nation
Thursday September 17, 2026 4:00pm - 4:30pm MDT
Delivering safe and reliable drinking water infrastructure to remote communities often requires innovative approaches that balance schedule, budget, technical complexity, and community priorities. In August 2025, Flowpoint Systems and Associated Engineering partnered with Sunchild First Nation in Alberta to deliver a fully integrated, turnkey modular water treatment system that was successfully commissioned in February 2026. This presentation, co-authored by Shane Beston (Sunchild First Nation), Hashanth Sasitharan (Associated Engineering, Calgary), and Jay Morrison (Flowpoint Systems), examines how a holistic team model between owner, consultant, and manufacturer enabled the successful execution of this fast-tracked project.
 
The session will explore the advantages and challenges of deploying a modular water treatment solution under an expedited timeline from multiple perspectives — including the owner’s experience navigating funding, risk allocation, governance, long-term operations, and community expectations. A key focus will be on the critical design considerations that enabled swift fabrication and installation, including strategic equipment selection, thoughtful site layout and area selection, and optimized equipment configuration tailored to modular construction constraints. The presentation will demonstrate how early alignment on these technical elements minimized rework, streamlined fabrication, and supported schedule certainty within a six-month delivery window.
 
In addition, the team will discuss the chosen contract structure and project delivery methodology, including why this approach was selected and how it supported collaboration, clarity of responsibility, and accelerated execution. The session will highlight how procurement strategy, clearly defined interfaces, and shared accountability between owner, consultant, and manufacturer contributed directly to project success.
 
The presentation will further address the broader benefits and limitations of modular systems, including reduced on-site construction requirements, improved quality control through off-site fabrication, footprint constraints, staging logistics, integration with existing infrastructure, lifecycle planning, and flexibility for future expansion.
 
By engaging the owner, consultant, and manufacturer from concept through commissioning, the team was able to streamline decision-making, align expectations, and resolve design-build interfaces quickly. The inclusion of the owner’s voice provides valuable insight into stakeholder engagement, operational readiness, and how early collaboration reduced project risk while strengthening long-term confidence in the system.
 
Attendees will gain practical lessons learned from all three perspectives, strategies for successful owner–consultant–manufacturer collaboration, and guidance on determining when modular construction and alternative delivery methods are the best fit for water treatment applications. This case study provides a replicable model for consulting engineers, manufacturers, and community leaders seeking innovative, efficient approaches to water system delivery across Western and Northern Canada.
Speakers
JM

Jay Morrison

Vice President, Flowpoint
For 28 years, Jay Morrison has helped communities across North America modernize water and wastewater systems with smarter, more sustainable solutions. As Vice President of Flowpoint Environmental Systems, he leads innovation in automated bulk water dispensing, septage receiving... Read More →
HS

Hashanth Sasitharan

Project Engineer, Indigenous and Regional Infrastructure, Associated Engineering Calgary
Hashanth Sasitharan is a professional engineer with Associated Engineering’s Calgary office, specializing in municipal water and wastewater infrastructure. He has experience delivering treatment facilities, pumping systems, and supporting infrastructure for communities across Alberta... Read More →
Thursday September 17, 2026 4:00pm - 4:30pm MDT
Campania A/B 2nf Floor, Delta Hotel
 
Friday, September 18
 

9:00am MDT

Stormwater Management in the North: Lessons from Whitehorse’s City-Wide Model Development
Friday September 18, 2026 9:00am - 9:30am MDT
Whitehorse’s stormwater system operates under a challenging mix of steep terrain, cold-climate hydrology, and limited monitoring data; conditions that demand a modelling approach beyond typical urban drainage assumptions. This work developed a city-wide stormwater modelling framework for the City of Whitehorse, including catchment delineation, construction of an integrated PCSWMM model, and advanced GIS workflows to evaluate drainage performance under historical conditions, climate change, and rain-on-snow scenarios. More than 850 catchments and 150 drainage networks were generated using high-resolution elevation and infrastructure datasets, revealing technical challenges related to snowmelt representation, parameter selection, connectivity assumptions, and large dataset management. Results identified capacity constraints, localized flooding mechanisms, culvert bottlenecks, and sediment-sensitive conveyance issues. Recommendations focus on improving GIS-based asset inventories, expanding long-term monitoring to support calibration, refining modelling methods for northern conditions, and strengthening defensible stormwater planning for cold-climate municipalities.
Speakers
Friday September 18, 2026 9:00am - 9:30am MDT
Campania A/B 2nf Floor, Delta Hotel

9:30am MDT

Data-Driven Headworks Design
Friday September 18, 2026 9:30am - 10:00am MDT
Each wastewater treatment facility faces unique influent characteristics, making site-specific screening evaluations critical for optimizing headworks performance. At Alexandria Renew Enterprises (AlexRenew), field testing was performed to assess existing coarse and fine mechanical screens and evaluate alternative configurations.
Using on-site screening capture testing, various combinations of coarse and fine sieve openings and geometries were tested under average dry-weather conditions. Results showed the existing coarse screens removed an average of 0.7 cubic feet of solids per million gallons (CF/MG). In contrast, a configuration of a 19 mm slotted coarse screen followed by a 6 mm perforated plate fine screen achieved an average Screen Capture Ratio of 52%—a projected threefold increase in solids removal.
Beyond capture efficiency, testing provided valuable insight into screen hydraulics, blinding tendencies, and compatibility with existing infrastructure. This approach demonstrates how field data can guide screen selection, improve debris removal, reduce downstream maintenance, and extend equipment service life.
The case underscores the value of empirical testing in headworks design. By quantifying capture rates, headloss behavior, and solids characteristics, utilities can make more informed upgrade decisions tailored to their specific flow conditions and operational priorities.
Speakers
JA

Jeff Austin

Hydro-Dyne Engineering

Friday September 18, 2026 9:30am - 10:00am MDT
Campania A/B 2nf Floor, Delta Hotel

10:00am MDT

Groundwater and Residential Development: The perpetual pumping sump pump problem
Friday September 18, 2026 10:00am - 10:30am MDT
In several Saskatoon neighbourhoods built after 2004, homeowners have raised concerns with the perpetual operation of foundation drainage sump pumps. Continuous pumping to the surface has created year-round issues such as algae growth, ice buildup and drainage onto driveways, sidewalks, lanes and adjacent parks.
The current workaround permits discharge of sump pump effluent into the sanitary sewer system during the winter months, resulting in reduction of sanitary sewer capacity and water being unnecessarily treated by the WWTP at additional cost. This does not address the summer discharge concerns and enforcement is lacking for switching back to surface discharge in the summer.


This has been an issue in Saskatoon for many years with previous mitigation strategies producing limited or short-term success. To address this, the City of Saskatoon launched a comprehensive review project in 2025. The project has completed a review of how other municipalities manage the issue, conducted a residential survey and completed an internal multi-departmental workshop to brainstorm solutions. 
Ongoing work includes feasibility assessments for the preferred options and once completed, engagement with the land development and home building industry will occur to understand the impacts of the preferred options. 


The presentation will provide a history of how this multi-decade issue was created, the results from the municipal scan and the residential survey. The preferred options will be presented and their positives and negatives discussed. If industry engagement is completed before the conference, these results will also be shared along with the project’s next steps towards a long-term resolution.


Speakers
VH

Vanessa Heilman

Geotechnical Engineering Specialist, City of Saskatoon
Vanessa is a geotechnical engineer with 7 years’ experience in a variety of geotechnical and brownfield development projects in the UK and a further 13 years’ experience of Canadian geotechnical projects. Since moving to Canada Vanessa has been involved in slope stability analysis... Read More →
Friday September 18, 2026 10:00am - 10:30am MDT
Campania A/B 2nf Floor, Delta Hotel

11:00am MDT

AMI 2.0: Unlocking Smart Meter Data for Proactive Leak Detection and Inflow and Infiltration (I&I) Insight
Friday September 18, 2026 11:00am - 11:30am MDT

Advanced Metering Infrastructure (AMI) is rapidly evolving from a billing-focused technology into a foundational data source for utility-wide operational intelligence. As utilities expand metering programs and pursue digital transformation initiatives, the next generation of AMI—AMI 2.0—enables organizations to leverage high-resolution consumption data to address persistent challenges such as non-revenue water, leak detection, and system inflow and infiltration (I&I) awareness.


By integrating AMI data with operational, hydraulic, and environmental datasets, Utilities can generate actionable insights across both customer and system levels. By integrating AMI data with operational, hydraulic, and environmental datasets, Utilities can generate actionable insights across both customer and system levels. Influenced by implementation work with the City of Immokalee, Florida, this approach demonstrates how continuous meter analytics can identify abnormal flow patterns, persistent consumption, and nighttime flow conditions that indicate leaks or operational inefficiencies.  When aggregated and contextualized, meter data also provides valuable system-level indicators that help utilities better understand flow anomalies and potential I&I impacts, enabling more targeted investigation and response.


AMI 2.0 shifts the role of smart meters from passive measurement devices ('cash registers') to active components of a utility’s digital ecosystem. By combining advanced analytics, data integration, and scalable enterprise architecture, utilities can move beyond reactive workflows toward proactive operations that improve water accountability, optimize field resources, and strengthen infrastructure planning.


As water metering adoption accelerates across regions such as Western Canada, utilities have an opportunity to design programs that maximize long-term value from the outset. Leveraging AMI data for both leak detection and broader system intelligence supports improved resiliency, operational efficiency, and measurable return on investment while establishing a scalable foundation for future analytics and AI-driven applications.

Speakers
avatar for Michele Samuels

Michele Samuels

Client Solutions Manager, Canada, Xylem Vue
Michele is passionate about innovation and the role that digital technologies play in driving operational and financial resiliency for customers across the water cycle. With more than 20 years of experience, she has seen the powerful impact that smart solutions, combined with consultative... Read More →
Friday September 18, 2026 11:00am - 11:30am MDT
Campania A/B 2nf Floor, Delta Hotel

11:30am MDT

Purpose and Benefits of Alarm Rationalization
Friday September 18, 2026 11:30am - 12:00pm MDT
We are inundated with information in all ways, shapes, and forms; from our cell phones, televisions, and computers, isolating information and presenting what information requires action has become essential. Standardized SCADA alarm systems are powerful tools that can be utilized in this process. It is imperative to provide warnings about developing situations so Operators can take timely corrective action. Alarms can be interruptive by nature and must be carefully managed to minimize the number of nuisance alarm activations. Unnecessary alarm activations can significantly drain operational staff resources in terms of staff time, after-hours call-outs, and workload in each plant's control room.
The International Society of Automation 18.2 describes systematically reviewing and documenting alarms to help diagnose and respond to abnormal situations. The standard outlines mandatory and recommended practices for a lifecycle approach to alarm management. Standardized work processes are used to design, implement, maintain, and monitor the alarm system.  
Speakers
avatar for Dawn Kuechle

Dawn Kuechle

Team Leader - System Integration / Operational & Digital Technologies, CIMA+
I have over 20 years of experience in SCADA system design and systems integration, with a strong background as both a developer and an educator. I specialize in building SCADA solutions with a focus on reliable communication between remote devices and the SCADA host, and I bring hands-on... Read More →
Friday September 18, 2026 11:30am - 12:00pm MDT
Campania A/B 2nf Floor, Delta Hotel
 
  • Filter By Date
  • Filter By Room
  • Filter By Type
  • Timezone


Share Modal

Share this link via

Or copy link

Filter sessions
Apply filters to sessions.